General Moly Announces Fourth Quarter and Full Year 2012 Results

Updated

General Moly Announces Fourth Quarter and Full Year 2012 Results

LAKEWOOD, Colo.--(BUSINESS WIRE)-- General Moly, Inc. (the "Company") (NYSE MKT:GMO) (TSX:GMO), a U.S.-based molybdenum mineral development, exploration and mining company, announced its unaudited financial results for the fourth quarter and full year ended December 31, 2012. Net loss for the three months ended December 31, 2012 was $2.0 million ($0.03 per share), compared to a loss of $2.9 million ($0.03 per share) for the year ago period. Net loss for the full year ended December 31, 2012 was $9.9 million ($0.11 per share), compared to a loss of $14.8 million ($0.16 per share) for the year ago period.

The Company's cash balance at December 31, 2012 was $68.3 million not including restricted cash compared to $22.4 million at September 30, 2012. During the fourth quarter, cash use of $22 million was the result of $18 million in Mt. Hope Project development, engineering and procurement costs and $4 million in General and Administrative expenses. This cash use was more than offset by the receipt of $104 million in contribution payments from POS-Minerals Corporation, a 20% joint venture partner on the Mt. Hope Project. The members of Eureka Moly, General Moly and POS-Minerals, agreed that $36 million of the contribution be held in a reserve account to maintain additional liquidity pending confirmation of a previously announced $665 million Chinese sourced Term Loan that is being negotiated with China Development Bank ("CDB").


Bruce D. Hansen, Chief Executive Officer of General Moly, said "We achieved a number of significant milestones in 2012, including receipt of all major federal and state operating permits for the Mt. Hope Project and the initiation of preliminary construction activities at the site. We also received more than $100 million in additional financing from POS-Minerals. Looking into 2013, we are moving aggressively to conclude our financing and start heavy construction at Mt. Hope in the spring. We will also push forward with feasibility work and permitting on Liberty, our second world-class molybdenum project, after Mt. Hope has commenced heavy construction."

MT. HOPE PROJECT PERMITTING UPDATE

As announced on October 12, 2012, the Mt. Hope Final Environmental Impact Statement ("EIS") Notice of Availability was published in the Federal Register. The public review period for the Final EIS ended on November 13, 2012. On November 16, 2012 the U.S. Bureau of Land Management issued a Record of Decision ("ROD") authorizing development of the Mt. Hope Project.

In addition to the ROD, three Nevada state-issued permits, the Air Quality Permit, the Reclamation Permit and the Water Pollution Control Permit were viewed as major environmental permits for the Mt. Hope Project. The Air Quality Permit was received on May 30, 2012, the Reclamation Permit was received on November 20, 2012 and the Water Pollution Control Permit was received on November 21, 2012.

Additionally, the State Archeologist at the Nevada State Office of the Bureau of Land Management issued an Archaeological Resource Protection Act Permit for the Mt. Hope Project treatment plan on November 29, 2012. On December 26, 2012, the Public Utilities Commission of Nevada granted a permit to construct a 230 kV power line that interconnects with Nevada Energy's transmission system at the existing Machacek Substation located near the town of Eureka, NV and extend it approximately 25 miles to the planned Mt. Hope Substation.

MT. HOPE PROJECT FINANCING UPDATE

After the ROD and three major Nevada state-issued permits were received, POS-Minerals Corporation pursuant to the terms of the LLC agreement for the development and operation of the Mt. Hope Project funded its final $56 million initial contribution, plus 20% of all costs the Company has spent on the Mt. Hope Project to date for a combined total payment of approximately $104 million. Hereafter, the Mt. Hope Project will be funded 80% by the Company and 20% by POS-Minerals Corporation. The members of Eureka Moly, General Moly and POS-Minerals, agreed that $36 million of the contribution be held in a reserve account to maintain additional liquidity pending confirmation of a previously announced $665 million Chinese sourced Term Loan that is being negotiated with China Development Bank.

As previously announced, the Company and Hanlong (USA) Mining ("Hanlong") on October 26, 2012, signed a Subordinated Loan Agreement ("Sub Debt Facility") under which Hanlong agreed to provide up to $125 million subject to certain conditions to assist the Company in financing capital cost increases. The Sub Debt Facility supplements a previously announced $665 million Chinese sourced Term Loan that is being negotiated with China Development Bank. The Company had previously announced a letter of intent related to this facility with Hanlong on August 1, 2012. Under the Sub Debt Facility, Hanlong will lend in two tranches. Tranche A in the amount of $75 million will be available to the Company during the Mt. Hope Project's construction period. Tranche B, in the amount of $50 million, will be available during the six-month period following the commencement of commercial production. Tranche A of the Sub Debt Facility can be reduced to the extent equipment is leased for the Mt. Hope Project by Eureka Moly, LLC. Both tranches of the Sub Debt Facility will mature 5 years after the achievement of commercial production at the Mt. Hope Project and will have mandatory payments of 50% of the Company's semi-annual net free cash flow after debt service payments on the CDB term loan and any other Mt. Hope Project funding requirements. The Sub Debt Facility will be subordinated to the CDB term loan, with covenants to follow the Term Loan, and will bear interest at 6-month LIBOR plus 4%, with interest paid semi-annually.

MT. HOPE PROJECT CONSTRUCTION UPDATE

Early construction activities are progressing as planned at the Mt. Hope Project site including cultural clearance, clearing and grubbing, wood harvesting, and the development of wells and water pipelines. Kautz Environmental Consultants has completed field mitigation activities for all 32 cultural sites identified in the Phase I Cultural Mitigation of the initial construction program. Official releases from the Bureau of Land Management and the State Historical Preservation Office have been obtained for 27 of the 32 cultural sites. Ames Construction mobilized in early January and has since cleared and grubbed approximately 1,000 acres in preparation for starting major earthworks. The mine, process plant, and tailings dam areas and associated roads have been substantially cleared. Ames has also commenced work on eight miles of water pipeline to supply construction water from the permitted well field to the plant site and will next establish site construction offices and communication systems. Additionally, TIC will soon begin the installation of seven miles of electrical power lines and will install the pumping stations to support the approximately 2,000 gallons per minute of construction water in preparation for heavy earthworks in the spring.

MT. HOPE PROJECT ENGINEERING AND EQUIPMENT PROCUREMENT UPDATE

Engineering efforts, which were paused in March 2009, were restarted in 2012 by M3 Engineering & Technology. Through December 31, 2012, Eureka Moly LLC has made deposits of $69.7 million on equipment orders and has paid $12.0 million into an escrow arrangement for electricity transmission services.

The Company has now ordered or purchased most of the long-lead milling equipment, haul trucks, mine production drills, and has entered into a non-firm agreement for the purchase of electric shovels. While equipment procurement has restarted, firm orders for some loading equipment and other process equipment will be placed shortly after completion of project financing expected before mid year 2013.

MOLYBDENUM MARKET UPDATE

During 2012, molybdenum prices traded in a relatively narrow dollar range between $10.83 and $14.95 per pound, according to Ryan's Notes, a ferro-alloy industry news and pricing publication. Prices are currently trading at $11.25 per pound.

Additional information on the Company's fourth quarter 2012 results will be available in General Moly's 2012 Form 10-K, which will be filed with the Securities and Exchange Commission and posted on the Company's website.

GENERAL MOLY, INC.

(A DEVELOPMENT STAGE COMPANY)

CONSOLIDATED BALANCE SHEETS


(In thousands except per share amounts)

December 31,

2012

December 31,

2011

ASSETS:

CURRENT ASSETS

Cash and cash equivalents

$

68,331

$

40,709

Deposits, prepaid expenses and other current assets

136

105

Total Current Assets

68,467

40,814

Mining properties, land and water rights — Note 4

170,967

143,732

Deposits on project property, plant and equipment

69,691

66,474

Restricted cash held at EMLLC

36,000

Restricted cash held for electricity transmission

12,013

12,005

Restricted cash held for reclamation bonds

6,991

1,133

Non-mining property and equipment, net

605

819

Capitalized debt issuance and loan commitment costs

17,794

3,136

Other assets

2,994

2,994

TOTAL ASSETS

$

385,522

$

271,107

LIABILITIES, CONTINGENTLY REDEEMABLE NONCONTROLLING INTEREST AND EQUITY:

CURRENT LIABILITIES

Accounts payable and accrued liabilities

$

10,133

$

4,568

Accrued advance royalties

500

8,950

Accrued payments to Agricultural Sustainability Trust and Hanlong

4,000

2,000

Current portion of long term debt

10,906

10,596

Total Current Liabilities

25,539

26,114

Provision for post closure reclamation and remediation costs

627

587

Deferred gain

1,100

1,150

Accrued advance royalties

4,700

Accrued payments to Agricultural Sustainability Trust

2,000

2,000

Long term debt, net of current portion

661

131

Other accrued liabilities

875

Total Liabilities

35,502

29,982

COMMITMENTS AND CONTINGENCIES — Note 10

CONTINGENTLY REDEEMABLE NONCONTROLLING INTEREST

201,880

98,073

EQUITY

Common stock, $0.001 par value; 200,000,000 shares authorized, 91,333,092 and 90,818,248 shares issued and outstanding, respectively

91

91

Additional paid-in capital

270,902

255,894

Accumulated deficit before exploration stage

(213

)

(213

)

Accumulated deficit during exploration and development stage

(122,640

)

(112,720

)

Total Equity

148,140

143,052

TOTAL LIABILITIES, CONTINGENTLY REDEEMABLE NONCONTROLLING INTEREST AND EQUITY

$

385,522

$

271,107

GENERAL MOLY, INC.

(A DEVELOPMENT STAGE COMPANY)

CONSOLIDATED STATEMENTS OF OPERATIONS AND COMPREHENSIVE LOSS


(In thousands, except per share amounts)

Years Ended

January 1, 2002

(Inception of

Exploration Stage)

December 31,

2012

December 31,

2011

December 31,

2010

to

December 31,

2012

REVENUES

$

$

$

$

OPERATING EXPENSES:

Exploration and evaluation

778

1,568

623

40,479

Writedowns of development and deposits

3,403

5,038

8,819

General and administrative expense

10,600

10,248

10,919

80,375

TOTAL OPERATING EXPENSES

11,378

15,219

16,580

129,673

LOSS FROM OPERATIONS

(11,378

)

(15,219

)

(16,580

)

(129,673

)

OTHER INCOME/(EXPENSE):

Interest and dividend income

6

21

13

4,068

Interest expense

(548

)

(250

)

(164

)

(962

)

Realized gain from sale of mining properties

2,000

2,000

TOTAL OTHER (EXPENSE)/INCOME, NET

1,458

(229

)

(151

)

5,106

LOSS BEFORE INCOME TAXES

(9,920

)

(15,448

)

(16,731

)

(124,567

)

Income Taxes

CONSOLIDATED NET LOSS

$

(9,920

)

$

(15,448

)

$

(16,731

)

$

(124,567

)

Less: Net loss attributable to contingently redeemable noncontrolling interest

680

1,008

1,927

NET LOSS ATTRIBUTABLE TO GENERAL MOLY, INC.

$

(9,920

)

$

(14,768

)

$

(15,723

)

$

(122,640

)

Basic and diluted net loss attributable to General Moly per share of common stock

$

(0.11

)

$

(0.16

)

$

(0.22

)

Weighted average number of shares outstanding — basic and diluted

91,230

90,588

72,987

COMPREHENSIVE LOSS

$

(9,920

)

$

(14,768

)

$

(15,723

)

$

(122,640

)

GENER

Advertisement