Sterlite Industries (India) Limited Production Release for the Second Quarter and Six Months Ended 3

Before you go, we thought you'd like these...
Before you go close icon

Sterlite Industries (India) Limited
Production Release for the Second Quarter and
Six Months Ended 30 September 2012

MUMBAI, India--(BUSINESS WIRE)-- Sterlite Industries (India) Limited today announced its production results for the Second Quarter (Q2) and Half Year (H1) ended 30 September 2012.


Highlights

  • Strong H1 integrated production of Silver and Lead at Zinc India, up 66% and 59% respectively
  • Record Power sales in Q2 and H1
 

Zinc - India

  Q2 Q1 H1
Particulars(in'000 tonnes, or as stated)FY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
ZINC INDIA       
Mined metal content190210(9%)187377398(5%)
Refined Zinc - Total163185(12%)161324378(14%)
Refined Zinc - Integrated153185(17%)157310376(17%)
Refined Zinc - Custom10--4142-
Refined Lead - Total1271760%31583375%
Refined Lead - Integrated241740%29533359%
Refined Lead - Custom3--25--
Silver - Total (in tonnes)2924986%821749681%
Silver - Integrated (in tonnes)804963%791609666%
Silver - Custom (in tonnes) 12 - - 3 14 -  
 

Mined metal production was 190,000 tonnes in Q2 and 377,000 tonnes in H1, as compared with 210,000 tonnes and 398,000 tonnes in the corresponding prior periods. The Sindesar Khurd (SK) mine continued to ramp-up well with mined metal production up 39% at 45,000 tonnes in H1.

In line with the mined metal production, integrated production of refined zinc was 153,000 tonnes in Q2 and 310,000 tonnes in H1. Integrated production of refined lead was 24,000 tonnes in Q2, and 53,000 tonnes in H1, up 40% and 59% respectively, driven by the ramp-up of the new 100kt Dariba lead smelter.

In line with the mine plan and earlier guidance, mined metal production in FY2013 is expected to be slightly higher than the previous year, with production in H2 FY2013 more than making up for marginally lower production in H1 FY2013 as compared with the corresponding prior period.

Integrated production of silver was 80 tonnes in Q2 and 160 tonnes in H1, up 63% and 66% respectively, driven by the ramp-up of SK mine and the new 100kt Dariba lead smelter.

The Rampura Agucha underground mine and Kayar mine projects are progressing well to deliver commercial production in FY2014. The Kayar mine produced developmental ore in Q2.

 

Zinc International

  Q2 Q1 H1
Particulars(in'000 tonnes, or as stated)FY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
ZINC INTERNATIONAL114114-106220233(5%)
Zinc -refined3737-367376(4%)
Mined metal content- BMM and Lisheen 77 77 - 70 147 157 (6%)
 

Total production of refined zinc and mined zinc-lead metal in concentrate (MIC) was 114,000 tonnes in Q2, in line with the corresponding prior period, and 5% lower at 220,000 in H1 in line with the current year's mine plan and on account of lower grades, as earlier guided.

 

Copper - India and Australia

  Q2 Q1 H1
Particulars(in'000 tonnes, or as stated)FY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
COPPER- INDIA / AUSTRALIA       
Copper - Mined metal content6514%7131113%
Copper - Cathodes 87 87 - 88 175 161 9%
 

Copper cathode production was 87,000 tonnes in Q2, in line with the corresponding prior period, and 9% higher at 175,000 tonnes in H1.

Mined metal production at Australia was 14% higher at 6,000 tonnes in Q2 and 13% higher at 13,000 tonnes in H1.

The first 80MW unit of the 160MW captive power plant at Tuticorin, which will predominantly provide power to the copper smelter, was synchronised during the quarter.

 

Aluminium

  Q2 Q1 H1
Particulars

(in'000 tonnes, or as stated)

FY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
ALUMINIUM       
Balco 63 60 4% 60 123 121 1%
 

The Balco Korba-II smelter continues to operate at its rated capacity.

Due to a delay in obtaining regulatory approvals, the first 300MW unit of the BALCO 1,200MW captive power plant is now expected to be synchronized in the current quarter. Thereafter, we plan to tap the first metal at the 325 ktpa Korba-III aluminium smelter in Q4 FY2013. For the 211mt coal block at BALCO, we are progressing well towards obtaining the second stage forest clearance, and thereafter we intend to commence mining this year.

Power

  Q2 Q1 H1
Particulars(in million units)FY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
POWER       
Total Power Sales2,4741,74842%2,4584,9333,41544%
SEL 31,9401,26753%1,9383,8792,40461%
Balco 270MW Power Sales346387(10%)338684811(16%)
HZL Wind Power 188 94 99% 182 370 200 85%
 

Power sales were 2,474 million units in Q2 and 4,933 million units in H1, 42%and 44% higher than the corresponding prior periods. This significant increase was primarily due to higher power sales from three units of the Jharsuguda 2,400MW power plant, operating at availability of over 80% and plant load factor (PLF) of 50% in H1, with the fourth unit generating under trial run. PLF of the Jharsuguda 2,400MW power plant was constrained due to evacuation limitations. We continue to work towards debottlenecking of our evacuation capacity, and target to enhance it by an additional 1,000MW transmission by Q4 FY2013.

Power sales were augmented by higher sales at HZL wind power, which was expanded by 150MW to 274MW last year.

Power sales at Balco 270 MW were 10% lower at 346 million units in Q2 and 16% lower at 684 million units in H1 due to lower demand.

Work at the Talwandi Sabo power project is progressing well and the first unit is now expected to be synchronized in Q2 FY2014.

 

Production Summary (Unaudited)

(in '000 tonnes, except as stated)

  Q2 Q1 H1
ParticularsFY2013 FY2012 % change YoYFY2013FY2013 FY2012 % change YoY
ZINC INDIA       
Mined metal content190210(9%)187377398(5%)
Refined Zinc - Total163185(12%)161324378(14%)
Refined Zinc - Integrated153185(17%)157310376(17%)
Refined Zinc - Custom10--4142-
Refined Lead - Total1271760%31583375%
Refined Lead - Integrated241740%29533359%
Refined Lead - Custom3--25--
Silver - Total (in tonnes)2924986%821749681%
Silver - Integrated (in tonnes)804963%791609666%
Silver - Custom (in tonnes)12- 314- 
ZINC INTERNATIONAL114114-106220233(5%)
Zinc -refined3737-367376(4%)
Mined metal content- BMM and Lisheen7777-70147157(6%)
COPPER- INDIA / AUSTRALIA       
Copper - Mined metal content6514%7131113%
Copper - Cathodes87870%881751619%
ALUMINIUM       
Balco63604%601231211%
POWER (in million units)       
Total Power Sales2,4741,74842%2,4584,9333,41544%
SEL 31,9401,26753%1,9383,8792,40461%<
Read Full Story

Want more news like this?

Sign up for Finance Report by AOL and get everything from business news to personal finance tips delivered directly to your inbox daily!

Subscribe to our other newsletters

Emails may offer personalized content or ads. Learn more. You may unsubscribe any time.

From Our Partners

Gift Finder Promo
More to Explore